The **How many Monte Carlo chart** shows the distribution of how many items your team can complete within a chosen timeframe.

It helps you answer the following questions:

- How many items can we realistically deliver within a sprint or interval?
- What is the probability of reaching a target scope or commitment?
- What can we deliver with 50%, 70%, or 85% confidence?
- How does varying capacity, backlog size, or throughput history change our expected output?
- Is our throughput predictable enough to support confident commitments, or do we need to adjust expectations?

## How to read the chart

> 📝 All settings shown in the chart are configurable.

#### How future delivery paths are simulated

![image-20251209-144505.png](media://8bb31f48-0dcc-4258-86e9-c342aafd6f33)

The How many Monte Carlo chart uses your team’s historical velocities to run thousands of simulated delivery paths and estimate how much work can be completed within a specific timeframe. In the example above, the simulation samples throughput from the last six sprints (1️⃣) and repeatedly “replays” future sprints by randomly drawing one past velocity per trial until the selected date, April 1, 2026 (2️⃣). The x-axis shows the resulting scopes in story points (3️⃣), while the y-axis shows how many trials completed that amount of work (4️⃣).

#### Interpret probability zones and targets

![image-20251209-144816.png](media://77b41cf2-1d32-4199-a5f6-6aef1d3791ee)

Results are colored red, amber, or green depending on their probability. In this example, 50% of trials completed 58.25 story points (5️⃣), and 85% of trials completed 43 story points (6️⃣). The target scope of 70 story points falls in the red zone (7️⃣), indicating that, under current conditions, the probability of completing that amount of work by the selected date is rather low.

#### Review the velocity data behind the forecast

![image-20251209-145002.png](media://15377f51-50e6-4c3f-b9a6-53f9cf1b56b8)

To understand which velocities were used in the simulation, review the Throughput graph below the forecast (8️⃣). If the selected data source has too little or irregular throughput, you can choose an alternative data source (9️⃣) in the **Forecast** menu to model from.

> 📝 <u>[Learn more about the Alternative throughput data](https://brokenbuild.atlassian.net/wiki/spaces/MTC/pages/4485447723)</u>

#### Model scenarios and track progress

![image-20251209-145603.png](media://28197a9c-63ce-4372-9ec3-31a84dc50edc)

You can also experiment with capacity allocation - for example, increasing capacity by 20% (1️⃣0️⃣) pushes the probability of completing the target scope in time to 50% (1️⃣2️⃣). As your delivery process evolves, the Target vs. Projection health metric (1️⃣3️⃣) helps you track whether you are moving closer to your planned milestones.

> 📝 <u>[Learn more about the capacity allocation coefficient](https://brokenbuild.atlassian.net/wiki/spaces/MTC/pages/4485447911)</u>

#### Use Monte Carlo to make reliable sprint commitments

![image-20251209-150848.png](media://363347cd-3b56-4cb0-a55d-32830c607a4a)

If you use the duration setting with a 1-sprint window instead of a specific date (1️⃣4️⃣), the chart can help you make a realistic sprint commitment and set expectations. In this example, the team can confidently commit to delivering 40–50 story points per sprint (1️⃣5️⃣), which corresponds to the 75%–85% confidence zone.